Whitson CM Contracting & Management, Inc.

Whitson Contracting & Management, Inc. | 11021 Via Frontera, Suite E • San Diego, CA 92127  |  Ph: 858-673-0966  |  Fax: 858-487-8355 

Ph: 858-673-0966
Fax: 858-487-8355

• CONSTRUCTION MANAGEMENT

SITE MAP

• ENVIRONMENTAL & STORMWATER

CONSTRUCTION MANAGEMENT
Carmel Valley Road Extension  |   Camino Del Norte Projects   |  Utility Projects

Whitson Contracting & Management, Inc. acts as an owner’s designated representative on engineering construction projects. WCM manages the design and permit process; writes all project bid documents; writes all contract documents including consultant agreements; manages the construction process; writes all contract change orders; manages SWPPP; manages the design engineers, City and or Caltrans, geotechnical engineer, surveyors, biologists, paleontologists, archeologists, and applicable utilities; closes out the project; assures City and/or Caltrans acceptance of the project; and obtains bond releases.
 
Carmel Valley Road Extension 
Project Description: 
Construction of a new roadway from the boundary of Black Mountain Ranch and 4S Ranch to the previously completed portion of Carmel Valley Road (approximately 7,100 lf). Scope of project included: site clearing, 2.2mil cy rock excavation, rough grading, storm drain systems, dry utility installations, cast-in-place pcc bridge, geogrid retaining walls, 6,200lf of 36” waterline, realignment of existing 36” RB pipeline 1,100lf 48” waterline, rock crushing, aggregate and CTB production, street lighting, traffic signals, minor concrete, ac paving, MBGR and fencing, irrigation and landscaping. Project issued subcontracts.

Project Value: 
Signs and Pinnick - Earthwork
TC Construction - Storm Drains and 48" Waterline
Erreca's - Bridge
Erreca's - 36" Waterline
Schilling Corp - Dry Utilities
Diamond Lanem -  CTB and AC Paving
GeoGrid - Retaining Walls
Area West Fence - MBGR and Fencing
Park West Landscape - Irrigation and Landscaping
American Concrete - Minor PCC
Pacific Erosion Control - SWPPP
Utility Agreements -
Engineers, Testing -
$1,541,000 (base contract)
$1,929,000 (base contract)
$2,318,000 (base contract)
$575,000 (base contract)
$1,792,000 (base contract)
$267,000 (base contract)
$217,000 (base contract)
$3,136,000 (base contract)
$329,000 (base contract)
$578,000 (base contract)
$370,000
$2,300,000

Camino Del Norte Projects

Camino Del Norte @ Interstate 15
Project Description:

Widen Camino Del Norte at Interstate.  Scope of project included: site clearing, tie-back retaining walls, soil nail retaining wall, CMU sound walls on CIDH foundations, rough grading, storm drain relocations, dry utility relocations, gas regulation station relocate,
street lighting, traffic signals, minor concrete, ac paving,
irrigation and landscaping.  Project issued a prime contract.any site development or public works contract.

Project Value:

FCI Constructors -                  
Utility Agreements -      
Engineers, Testing -  

$10,703,000 (base contract)
$1,750,000
$325,000

Camino Del Norte @ Bernardo Center Drive
Project Description:

Widen the intersection of Camino Del Norte and Bernardo Center Drive construct a cast-in-place pedestrian bridge.  Scope of project included site clearing, rock excavation, rough grading, storm drain relocations, dry utility relocations, pcc pedestrian bridge, masonry retaining walls, pcc retaining walls, street lighting, traffic signals, minor concrete, ac paving, irrigation and landscaping.  Project issued a prime contract.

Project Value:

Hazard Construction Co. -    
Utility Agreements - 
Engineers, Testing - 

$2,168,000 (base contract)
$750,000
$325,000

 

Utility Projects 
4S Ranch SS Lift Station
Project Description:

Construct CIP concrete pump station for waste water at 4S Ranch. Scope of project included: mass excavation, CIP concrete structure (buried), CMU control room building, 2 primary 12” pumps, secondary pumps, back-up generators, AC paving, site drainage, CMU sound walls… Project issued a prime contract.

Project Value:
TC Construction Co. - $2,539,000 (base contract)

Rancho Bernardo Road - 36" Waterline Relocation
Project Description:
Provide and install 5,750lf of 36” concrete mortar lined steel transmission waterline. Project issued as a subcontract.

Project Value:
T.C. Construction.Co. - $1,782,000 (base contract)
Engineers, Testing… - $125,000

Site Manager Sign In

Powered By
Yellow Pages
Yellow Pages